Hello All,
When a Resource plan is requested for specific group with hourly rate as $200 for 100 hours the planned cost is $20K on the Resource plan.
A cost plan record is created with total planned cost as $20K.
Once the Resource plan is "Confirmed and Allocated", the below fields
Resource Plan: "Confirmed/Allocated Cost" field is set to b.
Cost Plan: "Total Planned Cost" field is set to $5k
We understand that $5k is calculated from the "Default rate" from system property.
Please see the snippet below:
Could you please let us know how can we change this to get hourly rate from rate lines and update accordingly.
Thanks you!
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-07-2024 07:57 PM - edited 08-07-2024 07:59 PM
Hi @Knight Rider ,
Thanks for reaching out to community.
Looking at your post, I feel that you have not associated the rate model with project hence system is fetching the default rate i.e. $50 per hour.
Please try following:
Login as a project manager
Access the Financials from project form and associate the rate model, refer below screenshot
Try creating the resource plan again.
Hope this will resolve the pain point. If it does please mark the response as correct.
Happy SPM Learning !
Thank You!
Namita Mishra

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-07-2024 07:57 PM - edited 08-07-2024 07:59 PM
Hi @Knight Rider ,
Thanks for reaching out to community.
Looking at your post, I feel that you have not associated the rate model with project hence system is fetching the default rate i.e. $50 per hour.
Please try following:
Login as a project manager
Access the Financials from project form and associate the rate model, refer below screenshot
Try creating the resource plan again.
Hope this will resolve the pain point. If it does please mark the response as correct.
Happy SPM Learning !
Thank You!
Namita Mishra