Project On Hold - task status change and lose actauls

Jim Hughes1
Tera Contributor

We are using PPM, and when we place a project statue  to  On Hold, we have to change the tasks status as welll? is that correct behavior?  it seems that we are forced to move the project task status revert to "OPEN"  in order to save the project record to ON Hold state.

If I place a project on Hold, I would prefer NOT to change any of the task status..

Also, do not want to change task status to OPEN.

 

What is the expected behavior?

1 ACCEPTED SOLUTION

 

You can still add an "On-Hold" state and have no functionality that changes the task. Whatever was done on your instance has logic tied behind the "On-Hold" status. I would find that logic and turn it off.

View solution in original post

5 REPLIES 5

 

You can still add an "On-Hold" state and have no functionality that changes the task. Whatever was done on your instance has logic tied behind the "On-Hold" status. I would find that logic and turn it off.