Hello people!

 

I have a simple question...

 

Do you know what is the table for an agile board? I need to build a report with stories and COLUMNS. If a build it with the stories table I won'tt be able to see the columns so I need to get the agile board table

LeonelSandroni_0-1699021811301.png

 



Thank you!!!

1 REPLY 1

AndersBGS
Tera Patron
Tera Patron

Hi @Leonel Sandroni ,

 

The visual taskboard table is vtb_board where there is a relation to the rm_story table as task table and an related list to vtb_lane, which is the visual taskboard columns:

 

AndersBGS_0-1699023305273.png

AndersBGS_1-1699023392939.png

 

If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders 

 

 

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/