Resource (Allocated vs. Actual) chart in Program Workbench shows 0 across the Fiscal Year

odinx16
Kilo Contributor

In the Program workbench, while the Cost Planned vs Actual chart is populated, the Resource Allocated vs Actual shows 0 across. 

The fiscal year is selected and the various projects in the Program have Resource Plans submitted for the Project Tasks. Of course, there are also Time Cards for the Resource Plans.

Where does this data come from and what are we doing wrong?

Thank you,

Nick

1 ACCEPTED SOLUTION

sachin_namjoshi
Kilo Patron
Kilo Patron

Resource (Allocated vs. Actual): The chart displays the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the program. The actual time spent is taken from processed time cards for the projects.

 

Regards,

Sachin

View solution in original post

2 REPLIES 2

sachin_namjoshi
Kilo Patron
Kilo Patron

Resource (Allocated vs. Actual): The chart displays the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the program. The actual time spent is taken from processed time cards for the projects.

 

Regards,

Sachin

Hi. Thank you for your answer. That is correct, and in the mean time, I did find the cause for which it was not working. The BR for processing timecards was altered, and therefore they were not counted.