In the Program workbench, while the Cost Planned vs Actual chart is populated, the Resource Allocated vs Actual shows 0 across.
The fiscal year is selected and the various projects in the Program have Resource Plans submitted for the Project Tasks. Of course, there are also Time Cards for the Resource Plans.
Where does this data come from and what are we doing wrong?
Thank you,
Nick
Solved! Go to Solution.
- Labels:
-
Project Portfolio Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-10-2018 02:06 PM
Resource (Allocated vs. Actual): The chart displays the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the program. The actual time spent is taken from processed time cards for the projects.
Regards,
Sachin

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-10-2018 02:06 PM
Resource (Allocated vs. Actual): The chart displays the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the program. The actual time spent is taken from processed time cards for the projects.
Regards,
Sachin
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-17-2018 02:07 AM
Hi. Thank you for your answer. That is correct, and in the mean time, I did find the cause for which it was not working. The BR for processing timecards was altered, and therefore they were not counted.