Resource Plans are not showing in the Resource Allocation Workbench

Steve Kastelein
Giga Contributor

Any suggestions on why these requested resource plans are not showing up on the Allocation workbench for this group?

find_real_file.png 

 

find_real_file.png

 

Here is the filter on the Resource Allocation Board

find_real_file.png

10 REPLIES 10

Michael Meyers1
Tera Contributor

Hi Steve Kastelein, 

 

You don't have to create a "task" on the Project....it's just looking for the dates of the Demand/Project.  So, if you have a Resource Plan tied to the Project, you'd need to filter off of the project dates, as opposed to the Resource Plan dates.  You're definitely not the only one that feels this could be changed/improved, but currently, that's how it works.

 

Michael