Hi,
I'd like to insert the Christmas holidays (and other Italian holidays) in the Schedule for Project Management, but I do not know which is the best way to do this (Unforetunately i deleted the demo data present in the schedules and I have only the weekdays now).
Thanks,
Skender
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-23-2015 09:51 AM
I did it.
I inserted all Italian holidays in one new schedule and then added it from the default Project Management Schedule as a child.
the warning 'Warning: There are no active entries in this Schedule' was because I haven't put any future year and there were no repetition.
The 'tiny' thing to understand was why project started at 00:00:01 (and not at 09:00:00!) time when the planned start date was exactly a holiday and not a working day? This was because I should have put holiday end/finish time at the following day (so a working day!) at 08:59:59.
Now it works everything fine, except the Eastern, which changes every year...
Thanks a lot everyone,
Skender
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-17-2015 03:16 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-23-2015 07:17 AM
I'm just learning this today so can't help. But you may want to post this question here Project Portfolio Management.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-23-2015 07:31 AM
You could go to a demo instance, export the data you want from those default loads and import them into your instance. The correct way is to have them in a child schedule of your main schedule, like the 'US Holidays' schedule is a child of the '8-5 weekdays excluding holidays'.
To log into a demo instance, go to https://demo005.service-now.com/login.do and put in the user/password combination of admin/admin.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎03-23-2015 08:54 AM
Hi Skender,
You can create child schedule for all the holidays details - Using Schedules - ServiceNow Wiki
and then attach this child schedule to your parent Schedule for Project Management. You will find the same stuff on this link.
Thanks,
Ganesh