SPM: Task Planned End Date set to cancelled

GPenetito
Mega Expert

Hi team. The project Planned End Date is derived from the latest task Planned End Date

 

My question is, when I set a task to Cancelled, why would it continue to inform the Project Planned End Date?

 

In my example, the last Task in my project had a Planned End Date of 31/03/24. When I cancelled that task, the next latest task in my schedule was 28/02/24 - but the Project Planned End Date remained 31/03/24. Why is that? It seems that the only way around that is the delete the Task record which is bad practice 

0 REPLIES 0