I want to display the field values ​​of requested items in the list on my task screen.

I'd like to implement this without customizing the widget; is this possible?

I'd like to know where to make the adjustments.

 

ap.png

1 ACCEPTED SOLUTION

Rakesh_M
Mega Sage

Hi @bonsai ,
1. Open All >>> To-dos Configuration
2.Select and open Approval record.
3.Under Detail Row section you have Detail fields .
4.Add the required fields here .
Screenshot 2026-04-20 at 12.50.10 PM.png

regards
Rakesh

View solution in original post

5 REPLIES 5

Rakesh_M
Mega Sage

Hi @bonsai ,
1. Open All >>> To-dos Configuration
2.Select and open Approval record.
3.Under Detail Row section you have Detail fields .
4.Add the required fields here .
Screenshot 2026-04-20 at 12.50.10 PM.png

regards
Rakesh