Hello all fellow learners!
as I haven't found any article regarding the Agile Development 2.0 Simulator Micro Certification I will share what I have done on my simulator instance.
Summary
The Micro Certification consists of six main tasks.
- Request your simulator instance
- Verify the necessary plugins
- Import data
- Update sprint property
- Configure timesheet policy
- Activate data collection
Request your simulator instance
First step is to request you instance. Simply click on "". No Time for a cofe! The process is pretty fast and you will have your instance in a few seconds.
Verify the necessary plugins
Second step is to verify the installed plugins. Usually the setup takes care of it and no action is needed. By searching for "plugins" you can search for all installed and available plugins. The following should be already installed:
- Agile Development 2.0
- Agile Development 2.0 - ATF Tests
- Agile Development - Unified Backlog
- Scrum Programs
- Performance Analytics Content Pack for Agile 2.0
Is there one missing? No problem, just install it. Still not installed? In this unlikely case please raise a case to the NowLearning Team.
✔️Validate the task
Import data
Next step is to import some demo data to work with. You should find the link to an .xlsx file in the description of your task. Download it and note the path saved to.
Create a new data source (sys_data_source).
Do not forget to specify the "Header row"!
Save the new data source and stay at the form. Attach the .xlsx file directly to the data source:
To verify the data source simply test load the data:
View the loaded data and open the first entry:
Create now a new transform map (sys_transform_map) to transform your data into the correct target table (rm_story):
To map the fields use the "Auto Map Matching Fields". Verify the auto map by clicking "Mapping Assist":
Ensure the six columns are properly mapped and save the mapping.
Now the data can be transformed by clicking "Transform":
Verify the transform:
✔️Validate the task
Update sprint property
Fourth step is to update the standard sprint duration from 14 to 21 days.
There is a system property (sys_properties) called "com.snc.sdlc.scrum.pp.default_sprint_length" to specify the duration:
You can list edit the value as requested to 21.
Next is the creation of a new agile group. You can find it in the filter navigation by searching for "Agile group":
Update the group capacity to "45":
In the related list "Sprints" create a new one:
The new sprint will be set up with 21 days duration.
✔️Validate the task
Configure timesheet policy
To update the timesheet policy that users can automatically fill the time cards with the time spent to complete the task, configure the default policy (time_sheet_policy):
Check "Auto fill time card with time worked entries".
✔️Validate the task
Activate data collection
This step is a little tricky as the validation will not allow you to set all up in on go 😉
Open the data collection job (sysauto_pa) "[Scrum] Daily Data Collection" & switch to the correct application:
Update the "Relative start" to 60 & the "Run as" to any user with the "pa_admin" or "pa_data_collector" role:
Execute the job now! The logs should show several thousand processed entries:
Next step is to edit the data collection again and update the "Relative start" to "1" & check "Active" to activate the daily schedule.
✔️Validate the task
All done! I hope this the right inspiration for your next Micro Certification!
Happy learning!
If my answer helped you, please mark it as Helpful/Solution.
Thanks & many Regards - Manuel
Solved! Go to Solution.
- 6,738 Views
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-28-2022 12:54 PM
Hope this will help with the questions regarding the Simulator tasks 😎
If my answer helped you, please mark it as Helpful/Solution.
Thanks & many Regards - Manuel
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-28-2022 12:54 PM
Hope this will help with the questions regarding the Simulator tasks 😎
If my answer helped you, please mark it as Helpful/Solution.
Thanks & many Regards - Manuel
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-06-2024 12:34 PM
I was so stuck on this one, final step, wasn't in the right scope! YOU ROCK!!!!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-22-2025 11:44 AM
Thank you for sharing this detailed document. I was stuck in the import data and sprints, and your post helped me complete the micro-certification. Great job!!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-13-2025 10:19 AM
I got stuck at the last step, but your solution helped me even after 3 years. Thank you so much!