Hi everyone, 
 
I have catalog item where a variable end date (end_date, type = date) has to be filled in.
This catalog item has a flow that leads to 4 subflows. 
In a subflow I want to create two task where the custom field scheluded end date (u_scheduled_end_date, type = date) should be filled with the item variable end_date + 28 days resp. 56 days. 

I tried this script, but the field scheduled end date aren't filled. 

 

// Retrieve the RITM from the current task
var ritmGr = new GlideRecord('sc_req_item');
if (ritmGr.get(current.request_item)) { // request_item contains the RITM sys_id

    // Retrieve the end_date variable
    var endDate = ritmGr.variables.end_date;

    // Calculate the new date (24 days later)
    var gdEndDate = new GlideDate();
    gdEndDate.setValue(endDate);
    gdEndDate.addDays(24);  // Add 24 days

    // Set the u_scheduled_end_date to the task
    current.u_scheduled_end_date = gdEndDate.getValue(); // Date only (type Date)
    current.update(); // Update the task with the new value

 
What else could I try? 

4 REPLIES 4

Ankur Bawiskar
Tera Patron
Tera Patron

@AgnesvdM 

where have you written this script?

are you creating a custom flow action and calling it from subflow?

the logic should be this

    gdEndDate.addDaysUTC(24);

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
Certified Technical Architect  ||  9x ServiceNow MVP  ||  ServiceNow Community Leader

AgnesvdM
Tera Contributor

I create a Catalog task in an existing subflow  (in the workflow editor). 
Task table is sc_task.
I added the script in the 'advanced script'-section. 

@AgnesvdM 

is it a business rule or flow action?

please share some screenshots.

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
Certified Technical Architect  ||  9x ServiceNow MVP  ||  ServiceNow Community Leader

AgnesvdM
Tera Contributor

Dear Ankur, 

 
I have attached some screenshots. 
The first one is from the catalog item. The variable I want to take as starting point has the name end_date. This is a companies end date. 

When this catalog item is submitted, a ritm is created togehter with a lot of catalog tasks.  In the last picture you can find the taks where I want to have the scheduled end date filled in based on the given end date. As you can see, this field is ampty, even though I added UTC to the piece code, as you suggested. 

The middle one is a screenshot of the summary of the catalog task so you can see the database name of this field. 

So I want that, when the variable item end_date = january 1, 2025, two tasks are created with a scheduled and date +28 (2 weeks) and + 46 (4 weeks). 

I hope I make myself clear. 

Catalog item variable name.pngfield name scheduled end date.pngtasks without scheduled end date.png