Add new tasks for your projects and assign them to your team directly from the new Project Workspace.
始める前に
Role required: it_project_manager
手順
-
Open a project from the home page of Project Workspace.
-
Select Add Task.
A new row is added to the bottom of the data grid of the planning page, with New Task as the default name for the task.
Alternatively, select a project task row and click
the Add task below icon (
). This action adds a new task right below the task that you
selected.
-
Edit the details of the task.
For example, task name, planned dates, assigned to, and others.
- オプション:
Press the Enter key to save the details and create a row for another
task.
-
Click anywhere on the data grid outside the task fields to save the
details.
-
Assign a task to a user by updating the Assigned to
field.
The user who is assigned this task to, is sent an email notification and is
also notified in the ServiceNow® instance when they log
in.
For notifications to work, your admin must enable them by setting the
Project task assigned to notification record as
true in Email Notifications and Provider
Notifications.