Request resources
After you create a resource plan, request resources from the resource manager.
始める前に
Role required: it_project_manager, resource_user
このタスクについて
注:
If the resource type in the resource plan is a group, you can request resources
only if that group has active members.
手順
- Navigate to .
- Open a resource plan that is in the Planning state.
- Select Request.
タスクの結果
The resource plan moves to the Requested state and is ready for review by the resource manager.