Configure custom Risk rank and Risk value for a project

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:2分
  • Configure custom risk rank and value scores (such as High-Medium, Medium-Low, or Absolute-Low) to rate the impact and probability factors for a risk.

    始める前に

    Role required: pps_admin

    このタスクについて

    Use the Risk Value Lookup module to set up the risk rank and risk value for a specific combination of risk impact and probability. The system uses these values to determine the degree of risk (Absolute, High, Medium, Low) based on the impact and probability factors of a risk.

    The value in the Probability field is multiplied by the value of the Impact field to generate the values for the Risk rank and corresponding Risk value in the Risk form.

    By default, you can use the following impact, value, and probability scores for a risk to create a risk rank and risk value score:

    • Absolute
    • Low
    • Medium or Moderate
    • High
    For example, a risk might have high probability and medium impact but you might want to consider it as an overall low risk for the project. In that case, you would configure the Risk Value Matcher form with the following values:
    • Impact = 2 Medium
    • Risk Rank Color = Green
    • Probability = High
    • Probability Number = 1
    • Risk Value = 3 Low

    手順

    1. Navigate to All > Project Administration > Settings > Risk Value Lookup.
    2. Select New.
    3. On the form, fill in the fields.
      For more information, see Risk value matcher form.
    4. Select Submit.