Split resource assignments using Resource Management Workspace
Splitting a resource assignment at a specific date creates a resource assignment for the same user.
始める前に
- When you split a resource assignment, a new assignment is created from the selected date. Both the assignments are assigned to the same user retaining the state of the assignment.
- When you split a resource assignment, a new assignment is created from the selected date. Both the assignments are assigned to the same user with Approved state.
- If a resource assignment has actuals captured for a certain duration, you can split the work only at the dates where there are no actuals captured.
- Role required: resource_user, resource_manager
手順
タスクの結果
The resource assignment is split at the selected date and a copy of the resource assignment with new dates are displayed under the assignments of the selected resource.
Split resource assignment
Consider a resource assignment named Implement GenAI in docs assigned to Abel Tuter from July 16 through December 02. If you split the resource assignment at September 09, there will be two resource assignments with the same name and state assigned to Abel Tuter.One resource assignment ranges from July 16 to September 09, and the other assignment ranges from September 10 to December 02.
Here, you can see an overlap of efforts for Implement GenAI in docs in month of September because the split is happening from September 10.