Add new columns to the planning page
Display new columns on the planning page of the new project workspace so that your project managers can view custom fields for the project tasks on the planning page.
始める前に
Role required: it_project_manager
このタスクについて
The project tasks displayed in the planning page of the new project workspace show the fields as per the Project Workspace view of the pm_project_task table. To display new fields, you must personalize this Project Workspace view of the pm_project_task table.
手順
- Navigate to pm_project_task_list.do.
-
Change the view to Project Workspace.
- Right-click the header and select View.
- Select Project Workspace
-
Add the necessary columns to the list.
-
Select the Personalize List icon (
).
- Move the required fields from Available to Selected.
- Select OK.
-
Select the Personalize List icon (
タスクの結果
The Project Workspace view of the pm_project_task table is updated as per your changes. The planning page of the new project workspace reflects these changes.