Request a Hardware Asset Refresh
Use the Hardware Refresh request flow to track the aged hardware assets that are nearing the end of their life cycle. Replace them with new hardware assets.
始める前に
Role required: Inventory_user
このタスクについて
When hardware assets get old, their maintenance costs and risks of failure increase, while their performance decreases. You can choose to replace all the old hardware assets with the same or different models of new hardware assets. After your Hardware Asset Refresh request is approved, the Hardware Asset Refresh flow takes you through sourcing and it triggers the Hardware Asset Refresh Line flow. The Hardware Asset Refresh Line flow uses Refresh Line tasks to take you through the steps of preparing the new asset, scheduling it for delivery, deploying it, and reclaiming the aged asset.
The Flow Designer application is used to create the Hardware Asset Refresh flow and the Hardware Asset Refresh Line flow. While customizing the Hardware Asset Refresh module, don't remove or customize the Update Sourcing set Variable step in the Hardware Asset Refresh flow.
While customizing a Hardware Asset Refresh catalog item on the Catalog Item form, don't remove or change the following variables.
| Tabs in the Catalog Item | Variables |
|---|---|
| Variables | Type of refresh |
| Process | |
| Variable Sets | Hardware Asset Management process set |
| Hardware Asset Management sourcing set |
手順
タスクの結果
The aged assets are set to get refreshed. In the Hardware table under the Disposal related list of the aged assets, the Refresh request line field is populated.
An Order status page appears and it displays the details of the order. A request is created to source the new hardware assets and to replace the aged hardware assets. The Request form shows the total price of all the new hardware asset models.
Use Hardware Asset Refresh Lines tasks to replace the aged assets
Replace aged hardware assets by sourcing new hardware assets.
始める前に
- proc_user for sourcing.
- asset and itil for Refresh Line tasks.
このタスクについて
When refreshing hardware assets, you don't have to update the asset records manually. When closing the hardware asset refresh lines, the asset records and the assets are automatically updated. Close each task to go to the next task, complete the refresh, and reclaim the aged assets.
- Prepare asset task: Prepare the new asset before you hand it over to the requester. For example, install any software that's required.
- Schedule refresh task: Schedule a date to hand over the asset to the requester.
- Deploy new asset: Hand over the asset to the requester or install the asset at the requester's location if necessary.
- Reclaim aged asset: Collect the aged asset.
手順
タスクの結果
- The state of the aged asset changes to In stock.