Gantt chart

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:3分
  • A Gantt chart on the planning console is a visual representation of a project timeline that shows start and end dates of tasks, and the dependencies between tasks.

    Use Gantt charts to add and delete tasks, change task dates and dependencies, and assess the progress of the overall project.

    Gantt charts

    図 : 1. Gantt chart
    Example Gantt chart

    The critical path

    The critical path is highlighted in red on the Gantt chart to differentiate critical path tasks from standard tasks in blue. Not all tasks are part of the critical path, only those tasks that directly affect the finish date. Use the critical path to determine which tasks are driving the finish date. If schedule adjustments are necessary, consider making resource or other changes to those tasks on the critical path.

    The tasks that are not part of the critical path and can therefore be delayed are commonly called slack or float tasks. The Gantt chart shows the slack/float tasks by default, but calculations that deal with these tasks, such as how long they can be delayed without impacting the project, is not available.

    Milestones

    A milestone is a project task with a duration of 0. Use milestones to indicate important dates in a project. If necessary, create dependencies between tasks and milestones so that a task does not start until a milestone has been reached.
    図 : 2. Milestone
    Milestone example

    Color coding

    The colors of the task bars on the Gantt chart are based on the percent complete and state of the task. The default color coding available for project and tasks is shown:
    表 : 1. Color coding of project tasks
    Color Explanation
    Light blue bar
    図 : 3. Light blue bar
    Screenshot for Light blue bar
    Task is pending or open.
    Dark blue bar (full or partial)
    図 : 4. Dark blue bar
    Screenshot for dark blue bar
    The percentage complete is between 1% and 100%. The dark blue section indicates the percentage complete. The task can be in the Work in Progress state or Completed state.
    注:
    The colors of the task bars on the Gantt chart can be configured from portfolio or program workbench.

    SDLC phases

    Icons appear next to tasks to indicate what phase they belong to.
    表 : 2. Phase icons
    Icon Phase
    screenshot for Agile phase icon Agile phase.
    screenshot for testing phase icon Testing phase.
    注:
    Tasks in the waterfall phase do not display an icon.