Add an external dependency on planning console

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:4分
  • Add an external dependency between two projects on the planning console. Use the work breakdown structure (WBS) column of the planning console to create a dependency between the different projects tasks.

    始める前に

    Role required: it_project_manager

    手順

    1. Right-click a task in the WBS column of the planning console.
    2. Select Add External Dependency.
    3. On the Add dependency form, fill in the following fields:
      • Project: The predecessor project that the dependency is added from.
      • Task: The task in the predecessor project that the dependency is added from.
      • Dependency Type: The type of external dependency: Hard or Soft.
    4. Select OK.

    タスクの結果

    • A shadow task corresponding to the predecessor task appears in the WBS section of the planning console of the successor project. A similar shadow task corresponding to the successor task appears in the WBS section of the planning console of the predecessor project.

      A shadow task is shown as a grayed out task in WBS column.

    • A shadow task corresponding to the predecessor task appears in the Project Tasks related list on the successor project form. A similar shadow task for the successor task appears in the Project Tasks related list on the predecessor project form.
    • The Dependency column in WBS column of the planning console of the successor project shows the external dependency value between the projects and tasks. The external dependency value has the following format:

      {project_number}\{WBS_number}{dependency_type}+{lag_time}

      Where
      • project_number is the number of the predecessor project.
      • WBS_number is the number of the predecessor task in the relationship.
      • dependency_type is the finish to start dependency type that the application supports.
      • lag_time is the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers.
    注:
    The external dependencies are displayed only when the Hide External Dependencies switch on the planning console is turned off. However, the Dependency column in the WBS section of the successor project still shows the value of the external dependency.

    In the example below, an external dependency is created between two projects P1 and P2. P1T1 is a shadow task of predecessor project P1, and PRJ0010127\1fs+0 is the external dependency value in the Dependency column of the planning console of the successor project P2.

    External dependency example

    次のタスク

    Check for any external dependency related notifications that may impact the project or its tasks.