Planned Task Relationship form
Learn about the fields of planned task relationship form.
| Field | Description |
|---|---|
| Predecessor | The predecessor, or determiner, in the relationship. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks. |
| Successor | The successor in the relationship. The successor depends on the predecessor. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks. |
| Type | The type of relationship, which is always Predecessor of::Successor of. Do not change this value. |
| Sub Type | The type of dependency. |
| Lag | The lag time between the tasks. The Enter the days, hours, minutes, and seconds for the lag. Lag time can be positive or negative. |