Apply template to a blank project in project workspace

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:1分
  • When you create a new project in the project workspace, you can apply a template.

    始める前に

    Role required: it_project_manager

    このタスクについて

    A project created from the off-schedule project template honors the off-schedule tasks and adjusts the dates according to the given start date.

    When applying a template to a project, the project state is set to the default state. Activate the default project state (pm_project.state = -5), and use it as the default value as it is Out Of The Box. You can update the label for the State field to meet your requirements if Pending doesn't fit well.

    手順

    1. Navigate to All > Project > Projects > Project Workspace.
    2. In the project workspace header, select New.
    3. Enter the project name, select the start date, and select a template in Create Project dialog box.
    4. Select OK.