Create an attribute-based resource assignment

  • リリースバージョン: Australia
  • 更新日 2026年03月12日
  • 所要時間:2分
  • Create an attribute-based resource assignment in Project Workspace. You can pre-define attributes based on your requirement.

    始める前に

    Role required: pps_admin or it_project_manager

    手順

    1. Create a planning attribute.
      注:
      If the assignment is attribute-based, then the assignment is created in the Unassigned state. You should have the pps_admin role to configure the planning attributes.
    2. Navigate to All > Employee Profile > Employee Profiles.
    3. Create an employee profile.
      For more information, see Activate Employee Profile.
    4. Navigate to Workspaces > Project Workspace and open a project.
    5. From the Planning pane, double-click the Resource assignees field for a project task.

      You can assign the resources from both planning and resource assignment pane.

    6. From the resource assignee list, select a user or group and press Enter.
      You can create new custom attributes, such as location, in addition to group, skill, and role, and can also leverage these custom attributes to create resource assignments.

    タスクの結果

    A resource assignment record for an attribute is created and auto-saved.
    注:
    The Primary group, Primary skill, and Primary role attributes can be enabled for the Resource Management. You can create more attributes based on your requirement.