  • Use the Request Extension form to request extension of an allocated resource plan.

    表 : 1. Request Extension form
    Field Description
    Extend until Date until which you want to extend the resource plan and request for resources.
    Request type Type of request. Options include: FTE, Person Days, or Hours.
    FTE or Person days or Hours Number of units to request resources.

    The field appears when you select one of the options in the Request type field. Based on the selected request type, specify the unit.

    For more information, see Request type.