Hi Everyone,
I am trying to setup Data Separation. I have opted Organization lens in the data separation hierarchy.
For Supported Entities, I have enabled pm_project and pm_project_task. I also clicked on the Sync UI Action in list view.
I created an entity group mapping as well. But all projects associated to the Business Unit are visible to users outside the Group mentioned in the mapping.
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-23-2025 11:59 PM
Additional Info: This seems to work if the entity chosen is Department but does not work out as expected if the entity chosen is BU.