Kanban Board Drag and Drop of Connected Work Cards

ChristiansVC
Kilo Contributor

Hi,

I'm using a CWM Kanban board with referenced Connected Work items (e.g. Project Tasks).

The items can be edited normally via List View and the board groups them correctly into lanes. However, drag & drop always fails with:

"Please use form view to update the record"

The same board configuration works for native CWM tasks.

Is drag & drop currently supported for referenced Connected Work items, or is there additional configuration required?

 

Thanks!

1 ACCEPTED SOLUTION

Hemanth M
Tera Sage

Hi @ChristiansVC ,

 

its a current limitation for connect work items and its document officially here - https://www.servicenow.com/community/cwm-articles/cwm-connected-work-faqs/ta-p/3337946 

 

HemanthM_0-1787050352345.png

 

Hope this helps!

 

Accept and hit Helpful if it helps.

Thank you,
Hemanth
Certified Technical Architect (CTA), ServiceNow MVP 2024, 2025,2026

View solution in original post

1 REPLY 1

Hemanth M
Tera Sage

Hi @ChristiansVC ,

 

its a current limitation for connect work items and its document officially here - https://www.servicenow.com/community/cwm-articles/cwm-connected-work-faqs/ta-p/3337946 

 

HemanthM_0-1787050352345.png

 

Hope this helps!

 