Hello Experts,
We have Contracts and under contract related lists "Assets covered" are there
created Before BR insert /update to update the start and end dates its working fine.
Before BR insert /update
Table - clm_m2m_contract_asset
Requirement
Same w want to achieve for the after update the dates needs to update automatically.
We have tried but no luck, kindly support..
(function executeRule(current, previous /*null when async*/) {
var recordUpdated=false;
var asset = new GlideRecord("alm_asset");
asset.addQuery('sys_id',current.asset+"");
asset.query();
if (asset.next()){
if (current.contract.starts!=""){
asset.u_lease_contract_start=current.contract.starts+" 00:00:01";
}
if (current.contract.ends!=""){
asset.u_lease_contract_end=current.contract.ends+" 23:59:59";
}
asset.u_lease_contract=true;
asset.update();
}
})(current, previous);
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2024 11:28 PM
Hi @akin9
Oops. Just correct these line below. it should do the trick.
grAsset.u_lease_contract_start=current.starts+" 00:00:01";
grAsset.u_lease_contract_end=current.ends+" 23:59:59";
Cheers,
Tai Vu
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2024 07:39 PM
Hi @akin9
Are you getting any error ? Did you checked if your Business rule is being called or not ? I would suggest you to check via Business Rule Debugger whether your Business rule is getting fired or not ? Also, do check for any conflicts with other existing business rules.
Thanks & Regards
Amit Verma
Please mark this response as correct and helpful if it assisted you with your question.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2024 08:09 PM
Hi @Amit Verma
Thanks for Quick reply!
above script is working fine its for before inset/update/
same i want to achieve for after date field changes script
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2024 08:42 PM
Hi @akin9
Since you're performing update related, your business rule above should be an After one, that runs on the clm_m2m_contract_asset table.
Ref: Prevent Recursive Business Rules
And to handle the date get changes on the contract table, you can have one more after rule that will query all asset covered and update it.
Sample.
After/Async insert/update
Conditions: Start date changes || End date changes
(function executeRule(current, previous /*null when async*/) {
var gr = new GlideRecord('clm_m2m_contract_asset');
gr.addQuery('contract', current.getUniqueValue());
gr.query();
while(gr.next()){
var grAsset = gr.asset.getRefRecord();
if(grAsset.isValidRecord()){
grAsset.u_lease_contract_start=current.contract.starts+" 00:00:01";
grAsset.u_lease_contract_end=current.contract.ends+" 23:59:59";
grAsset.u_lease_contract=true;
grAsset.update();
}
}
})(current, previous);
Cheers,
Tai Vu
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2024 09:56 PM
Hi @Tai Vu ,
Thanks for the quick reply!
Already My above script Before BR is running fine. that's also needed.
now contract extended and date is updated same need to populate on
related lists "Assets covered".
I have tried the script unfortunately not working. pls correct me if wrong