change calendar

Bharath39
Tera Contributor

How to create change calendar

 

Thanks and regards

3 REPLIES 3

Community Alums
Not applicable

Hi @Bharath39 ,

You can create a change schedule to view all scheduled changes, change tasks, blackout periods, maintenance windows for any given date, week, month, or year.

Before you begin

  • You have activated Change Management - Change Schedule plugin (com.snc.change_management.soc).
  • Role required: itil, sn_chg_soc.change_soc_admin, sn_change_role, sn_change_write roles, sn_change_write, or admin
Note:
  • A user with an ITIL role can create a Change Schedule definition and view the schedule definition that they have created.
  • An admin or a change schedule administrator can read or edit all Change Schedule definitions.

Procedure

  1. Navigate to All > Change > Schedules > Change Schedules and click New.
  2. On the form, fill in the fields.
    New Change Schedule form
    Field Description
    Name Name of the change schedule.
    Start date field Field from the change request form that indicates the start date as an example planned start date.
    End date field Field from the change request form that indicates the end date as an example planned end date.
    Condition Conditions that determine which change requests display in the Change Schedule interface and the order in which those change requests are sorted.
  3. Click Submit.
    The change schedule is displayed in the timeline view.

Also,

You can define a change schedule from a change schedule definition record. Change schedule definitions help you to define the content that displays in the change summary popover, the users, groups or roles with whom a schedule is to be shared, and related span style colors.

Before you begin

  • You have activated Change Management - Change Schedule plugin (com.snc.change_management.soc).
  • Role required: itil, sn_chg_soc.change_soc_admin, sn_change_role, sn_change_write roles, sn_change_write, or admin

About this task

To create a new Change Schedule, specify the start and end date fields that you want to be represented in the user interface and also specify the conditions to determine which change requests to display.

Procedure

  1. Navigate to All > Change > Schedules > Change Schedule Definitions and click New.
  2. On the form, fill in the fields.
    Change Schedule Definition form
    Field Description
    Name Name of the change schedule.
    Active Check box to select if a schedule is active.
    Changes
    Start date field Field from the change request form that determines the start date of the span.
    End date field Field from the change request form that determines the end date of the span.
    Condition

    Conditions which determine which change requests display in the Change Schedule interface and the order those change requests are sorted.

    Record Summary
    Left column fields List of fields which appear on the left column of the record summary pop-up. The record summary pop-up appears when you click any span on the change schedule timeline.
    Right column fields List of fields that appear on the right of the window when you click any span on the change schedule timeline. The record summary pop-up appears when you click any span on the change schedule timeline.
    Blackout and Maintenance
    Show blackout window Check box to select if blackout window associated to a change request appears in the change schedule timeline.
    Blackout window color Color to represent blackout window in the change schedule timeline.
    Show maintenance window Check box to select if maintenance window associated to a change request appears in the change schedule.
    Maintenance window color Color to represent maintenance window in the change schedule timeline.
    Sharing
    Share with Option to share the schedule with everyone associated with the change or with specific users and groups.
    Owner Owner of the change schedule.
    Group Owner Group that owns a change schedule and has administrative rights to the change schedule.
    Related Link
    Show Schedule Link to the change schedule that you have defined.
    Related Lists
    Related Definitions Details of related child schedules
    Style Rules Options to define style conditions to determine the color of a span using a condition builder. For example, if you want all changes of type Emergency to show as a red span, a span style can be defined for that condition.
  3. Click Submit.

 

I have followed the instructions to create a change schedule but cannot see any maintainace records on the display - does this mean that the mainainance records need to be associated to a change record when they are created ?    

Show maintenance window

Check box to select if maintenance window associated to a change request appears in the change schedule.

 

aholiday
ServiceNow Employee
ServiceNow Employee

Realize your ask is from some time ago but on the chance others come across this,

A scheduled change needs to appear in context of change schedule view, also check schedule configuration to see maintenance / black out schedules turned on. 

For example, when I created a demo change record, maintenance and blackout schedules appeared in view along with the demo change record (see screenshot).

 

Screenshot 2025-05-09 at 9.23.00 AM.png