Hi guys,

I created a condition in a workflow to wait for assigned tasks to be complete... however the workflow doesn't advance to the next activity after I have done the change on the task record that would allow the next activity to run.

This is what I have one the code.

// Set the variable 'answer' to true or false to indicate if the condition has been met or not.

answer = true;

var gr_tsk = new GlideRecord("change_task");

gr_tsk.addQuery('change_request', current.sys_id);

gr_tsk.addQuery('u_accept_task', '==', 'Yes');

gr_tsk.addQuery('wf_activity', '');

gr_tsk.query();

if (gr_tsk.next()) {

    answer = true;

} else {

    answer = false;

}

Thanks for your support.

1 ACCEPTED SOLUTION

The wait for script could then be something like this:



var gr_tsk = new GlideRecord("change_task");


gr_tsk.addEncodedQuery('state<3^change_request=' + current.sys_id);


// gr_tsk.addQuery('u_accept_task','Yes'); // I'm not sure/clear why you need this


//gr_tsk.addQuery('wf_activity', ''); // neither sure/clear why you need this.


gr_tsk.query();


if (gr_tsk.hasNext()) {


    answer = false; // if there's at least one record open then continue waiting


} else {


    answer = true; // if there's no records found then exit the wait for activity


}



Thanks,


Berny


View solution in original post

26 REPLIES 26

manikorada
ServiceNow Employee
ServiceNow Employee

Jesus,



If you are doing these for manual change tasks, then for manual change tasks the 'parent' field is not populated with Change request.


The business rule which is resposnible to move the workflow on parent is 'SNC - Run Parent workflows', so you need to mimic that business rule to run on Change Task but instead of using 'parent' field use ;'change_request' field.


Basically I need to enable a UI action based on the updates from the child change tasks.


Also, what if I want to update the change request from the change task workflow?


Mani,



Look at this post Re: I require a Workflow wait for condition to wait for 4 change tasks to complete before moving to ...