I am accessing the Work Order Templates module and created a record for Work Order and Work Order Task. However, when it was associated in the Planned Maintenance Schedule, it is not generating a Work order task. 

olimanalo_0-1719890756285.png

olimanalo_1-1719890850043.png

Thank you,

1 ACCEPTED SOLUTION

olimanalo
Mega Guru
Mega Guru

Hello everyone,

 

Thank you for the inputs. We have achieved the solution by doing a flow designer to automate creation of Work Order tasks in Work Order Template

View solution in original post

7 REPLIES 7

Hi @Sid_Takali,

 

That is not the answer I am looking for. We need to have work order task added to the work order once planned maintenance has been created