Join the #BuildWithBuildAgent Challenge! Get recognized, earn exclusive swag, and inspire the ServiceNow Community with what you can build using Build Agent.  Join the Challenge.

Work Order Task not generating under a Work Order in Planned Maintenance

olimanalo
Mega Guru

I am accessing the Work Order Templates module and created a record for Work Order and Work Order Task. However, when it was associated in the Planned Maintenance Schedule, it is not generating a Work order task. 

olimanalo_0-1719890756285.png

olimanalo_1-1719890850043.png

Thank you,

1 ACCEPTED SOLUTION

olimanalo
Mega Guru

Hello everyone,

 

Thank you for the inputs. We have achieved the solution by doing a flow designer to automate creation of Work Order tasks in Work Order Template

View solution in original post

7 REPLIES 7

Hi @Sid_Takali,

 

That is not the answer I am looking for. We need to have work order task added to the work order once planned maintenance has been created

olimanalo
Mega Guru

Hello everyone,

 

Thank you for the inputs. We have achieved the solution by doing a flow designer to automate creation of Work Order tasks in Work Order Template