‎11-27-2024 05:58 AM
The SAFe Epic object holds values for WSJF scoring, which we integrate with the planning item for the same SAFe Epic.
However, when the planning item is added to a portfolio plan with WSJF as the scoring framework, I want to sync the values of the scoring fields with the values in the planning item.
(sn_align_core_planning_item.scoring["wsjf_score"] = sn_align_core_scrum_epic.wsjf_score)
How can I automatically update the scoring values of the planning item once the planning item is added to the portfolio plan?
- 675 Views
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Thursday
Hello! Floating this question~
Relatedly, in Table: Planning Item [sn_align_core_planning_item], I can't see WSJF scoring values for non-SAFe Epic objects. Do WSJF scoring values need to be created then added at the parent planning item-level or at the planning item demand/project-level (PiD, PiP) in the table list view and portfolio plan list columns?
We plan to have use the scores for Demand planning items vs. EAP planning items, likely similar to the use case described in this forum article.
sn_align_core_planning_item displays these columns, but not for PiD, PiP:
- User business value [EAP planning item]
- Time criticality [EAP planning item]
- Risk reduction [EAP planning item]
- Job size [EAP planning item]
- WSJF score [EAP planning item]