Is it required to close out all the Control test issues that were made in Audit Engagement before it can be considered as complete or as closed?

1 ACCEPTED SOLUTION

Not applicable

Hi @jajay ,

As per the Product Design for Audit Management, you will have to close any Control Test, Issues, Tasks or any activities else, the Engagement won't go to closed state, it would be in "Follow-up" or" Closed Incomplete".

 

View solution in original post

1 REPLY 1

Not applicable

Hi @jajay ,

As per the Product Design for Audit Management, you will have to close any Control Test, Issues, Tasks or any activities else, the Engagement won't go to closed state, it would be in "Follow-up" or" Closed Incomplete".