Is it possible to create several (child) response tasks in a single risk?

Nagashree5
Tera Contributor

Hi All,

 

Is it possible to create several (child) response tasks in a single risk? The reason is that sometimes, the mitigation plan involves more than 1 task and/or different owner. 

 

Thanks in Advance.

2 REPLIES 2

Community Alums
Not applicable

Hi @Nagashree5 ,

As per OOTB, it's not possible, as you might have to close the Response task to create another one.

However, If you want the functionality to change to create multiple Risk response tasks then , you will have to change or inactivate the OOTB Business rule called "Create related task for respond state" . 

 

 

ShafrazMubarak
Giga Guru

In Advanced Risk, you can create 4 different types of risk response tasks under a risk (Transfer, Mitigate, Avoid or Accept). The combination of these tasks are possible under a single risk. 

You cannot create multiple risk response tasks for the same response type. 

 

We have customized few solutions to create child tasks under the selected risk response task. But this has to be done as a customization.