Hi,
The Fieldwork state is now at 100% complete, The next state would be is the Request Approval. Can we move it to Request Approval state and have it approved even though the are still open Audit Issues remaining?
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-28-2023 09:38 AM
Yes, technically it is possible. ENG will remain in Follow up state until all open tasks, issues and Milestones get closed.