Trying to figure out a way to make a P3 - High but not sure on the selection/adding of choice to make
looking for ideas:
What if I just added in a selection to be:
Impact: 3- Medium <-- add in this as a new selection
Urgency: 1- High
Priority = P3 High
What other selection could I use for it to be P3-High
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 12:55 PM
If you are not able to change the OOBT matrix, then i would suggest you to make custom impact, priority and urgency and use the priority look up tool to establish relationship between them.
e.g.: make new impact - "1.5 -Moderately High" and urgency - "1.5 -Moderately High" and use this 2 to establish relationship to P3-high priority.
Note: Please mark below answers as correct answer and helpful if it resolved, or mark this helpful if this help you to reach towards solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 10:47 AM - edited 11-22-2022 10:48 AM
Please find below the matrix P3 :
Please mark this as correct answer and helpful if it resolved, or mark this helpful if this help you to reach towards solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 10:52 AM
So if we wanted to create a new priority which would be 3 - High / P3 - High
what would you add to the impact and urgency in order to make a P3 - high
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 12:10 PM
If I need to create a new priority which would be 3 - High / P3 - High, I would add :
impact :1 high and urgency :3 low
impact :3 low and urgency :1 high
Please mark this as correct answer and helpful if it resolved, or mark this helpful if this help you to reach towards solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 12:35 PM
My team has mentioned we cannot use existing selection as it would break other tickets in reports tables
Would you happen to know what selection we could create as we would need to figure out how to name and add selection to make a P3 - High thank you for your time and help!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2022 12:55 PM
If you are not able to change the OOBT matrix, then i would suggest you to make custom impact, priority and urgency and use the priority look up tool to establish relationship between them.
e.g.: make new impact - "1.5 -Moderately High" and urgency - "1.5 -Moderately High" and use this 2 to establish relationship to P3-high priority.