actual start and end dates needs to be auto populated when the changes moves from Scheldule ==> Implement

tapu
Giga Contributor

whenever we change the state from scheduled to implement at that time actual start date and end date should be auto-populate. 

1 ACCEPTED SOLUTION

Did you check how the dates are being set?

Check BRs : Change Model: Set work start & Change Model: Set work end

Best Regards
Aman Kumar

View solution in original post

4 REPLIES 4

Harish KM
Kilo Patron
Kilo Patron

HI actual start date and end date should be auto-populate from where?

Regards
Harish

Aman Kumar S
Kilo Patron

You will need to alter "ChangeRequestStateModelSNC_normal" to modify the OOB behavior

Best Regards
Aman Kumar

what we need to modify here ?

Did you check how the dates are being set?

Check BRs : Change Model: Set work start & Change Model: Set work end

Best Regards