01-24-2024 12:57 AM
Hi all.
What are the "actual start time" and "actual end time" of project tasks?
I have confirmed that I can change the date to any date, but when I try to change the time as well, it is set back to the original time.
For example, if I change the "Actual Start Time" from 16:30 to 9:00 in the image, the "Actual Start Time" is set back to 16:30 and the "Actual End Time" is set to 2023-12-29 09:30:00, which is only ahead of the "Actual duration".
What is the cause?

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-24-2024 01:02 AM
Hi,
It is well documented on doc. Please follow link for a check.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-24-2024 01:29 AM
Hi @RyoyaFukuda
If i speak from experience, Actual Start /end time is mainly used to track the actual efforts , means as soon as your record move to In progress or in case of change move to Implement, actual start time populated
Changing it manual is not and never be a good or best practice. What I can suggest, make this field read only and auto populate base on the condition.
You can refer to below image
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************