Resolved! If we export a Project Plan, will the export include any Attachments for the Tasks?
If we export a Project Plan, will the export include any Attachments for the Tasks?
If we export a Project Plan, will the export include any Attachments for the Tasks?
I am trying to run a simple report to produce a list of users that are in multiple resource groups. I think I am close, but my lack javascript skills (and probably script include config!) is got me stumped. My script looks like this: function getDup...
Hello, We are in the process of undertaking a Proof of Concept to see whether the Resource Management functionality in SPM is effective and fit for purpose. We are keen to understand whether there are any good examples of resource dashboards, MI etc...
Why do we calculate the inverse of risk and size in Demands. But not for ProjectsFor DemandsScore = ((10 - risk) + (10 - size) + value)/3For ProjectsScore = (risk + size + value) / 3 Looking at the scoring since We have a scenario where we want to us...
A customer is asking how to set the reference date for EAC calculation. EAC = Sum of all actuals for past fiscal periods + Sum of functional cost for future fiscal periods Suppose it’s May 31 today – EAC still is; Sum of actuals for Jan. to Apr. + Su...
When we started our Demand Management journey last year, we reviewed several demonstrations, webinars, etc. During that time we saw a screenshot of a dashboard that we just cannot find. ITBM L1 Demand Manager Dashboard Can anybody point us in the r...
I want to build an indicator that shows the average time (days or hours) that demands are in each state. The purpose is to identify bottlenecks in the demand's flow. Performance Analytics only have indicators with the entire time (from start to end) ...
The way our organization is set up, we have the need to have several Sprints per team at the same time. But, this is not allowed. Has anyone run into this and found a good solution? We've just been creating more and more assignment groups and the man...
I see fields "Approved start date" and "Approved end date" on status report form ( Table: project_status). By config dictionary I see that it is on table project_status. Questions: 1. What is the purpose of these two fields and from where these field...
Posted this on the ITSM forum by mistake earlier, but I need help with a state handling issue a customer is experiencing. When a project is set to Closed Complete and the user selects "OK" on the prompt which states that all project tasks will be clo...
In Demand there are 2 due date fields.1. Due Date (requested_by)2. Due Date (due_date) When you populate Due Date (requested_by) this auto-populates Due_Date (due_date), but I have not been able to find what populates this. I have watched the field a...
Can someone help me understand how an expense line can be created against a Demand? We would like to start tracking expenses on a Demand, but it's not working for us. Per the documentation, I should be able to select a cost plan against which I want...
As a resource manager i need to create a dashboard board to see the total Capacity of (a) Group(s) against the sum of al operational plans for the group and resource reservations for projects (Requested+Committed+Allocated. How do i define, or where ...
I tried creating an example Project with Project calculation set to MANUAL.Also, created Project task and child Project task. and played around with changing the planned dates for these tasks. the Project seem to be updated with the child planned tas...
I have resource roles and all roles have their hourly rate set to $0:However, when I create resource plans, their are still costs that are being calculated:My assumption is that if all of my hourly rates are set to $0, shouldn't all of my planned cos...