why Actual Cost and Actual hours are not calculating from Time card in ResourcePlan

chanikya
Tera Guru

Actual Cost and Actual hours are not calculating from Time card   in Resource Plan.

2.png

1 ACCEPTED SOLUTION

This business rule - Accumulate Hours/Cost to Resource Plan - is inactive. Is there a reason for that?


View solution in original post

9 REPLIES 9

Michael Fry1
Kilo Patron

is the Time Card Resource Plan field populated?


2.png





in Real time when time card is created , Time card hours are added into Actual Hours filed,     and


                                                                                                                                Resourcepaln amount are added into Actual cost




but here it is not effecting , please help me what I do here


Please note below



Actual Cost[Read-only] Based on the same time cards used for the Actual Hours, the actual cost is calculated using the cost of each user and the hours the user worked. Used to inform resource requesters and resource managers of actual costs based on the actual hours that user resources added on their time cards.



is time card approved?



REgardsm


Sacin


Time card was approved, ...



But hours and cost are not reflected



What I have to do


If you are interested


Dev 19708


User id:John.adams


Pawd: 1234