Change Management - Scheduled Time

Van L
Kilo Contributor

It has been proposed by a vendor that our normal changes include in the schedule any potential roll back time when creating the schedule for the normal change. I have not been able to find best practices to decide on this. Are there any thoughts on schedules and normal changes? 

2 REPLIES 2

aalanko
Tera Contributor

My organization includes time to validate a change during the scheduled window.  We do not plan for a roll back.  I am curious as to why they suggest this? 

Van L
Kilo Contributor

This is still puzzling me as well. I do not see the benefit of extending the change window. In the long run, it could prevent other changes from happening if conflict calendars start to overlap within the organization.