Industrial Guided Task form
The following table describes the field values for the Industrial Guided Task form in Industrial Connected Workforce Mobile Experience.
| Field | Description |
|---|---|
| Short description | Short description of the guided task. This field is automatically filled with the name of the standard from which the task is being created. |
| Priority | Priority of the guided task. Options are:
If not selected, the default value is 3 - Today. |
| Planned start | Planned start of the task execution. |
| Planned end | Planned end of the task execution. |
| Due date | Date by which the task is to be executed. If not set, this field calculated based on priority. |
| Functional location | Industrial facility work area where the task is to be completed. The location is defined using the ISA-95 standard. |
| Equipment | Machine to which the task relates. This field is automatically filled if equipment is specified in the standard. |
| Assigned to | User that the task has been assigned to. |