I'm looking for some ideas to help a client that wants to establish a percentage of their work to be placed as Resource Plans, while leaving the modern Resource Assignments per project/demand requests, have you had anyone do this successfully?
Their allocation ceiling for admin work varies per person, and they want a way to show the full capacity in RMW. They used to be able to do this seamlessly when everything was Resource Plans.
The biggest reason for this ask is visibility to full capacity remaining flexible to the individual, or group through combining both capabilities.
Thanks in advance!
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-13-2026 02:46 AM - edited 10-13-2026 02:50 AM
Hi Ellie,
Have you evaluated **Operational Resource Assignments** in Resource Management Workspace for the admin-work allocation?
ServiceNow supports creating operational assignments separately from project/demand assignments. This looks like the closest OOTB fit for your requirement to retain project/demand assignments while allocating a percentage of each person's capacity to admin work.
I'd test this with different admin-allocation percentages for individual resources and verify how those assignments affect the remaining-capacity and utilization views in RMW.
Create resource assignments in Resource Management Workspace
https://www.servicenow.com/docs/r/it-business-management/resource-management/create-ra-rmw.html
If the operational assignments don't provide the required percentage-based flexibility or capacity roll-up in your release, that specific gap needs to be validated before considering customization.
Helpful? Please mark the response as Accepted Solution ✅ and close the thread, this helps future readers find the solution faster.
Regards,
Sachinvic
✨ArchX Certified | ✨ 16x ServiceNow AI MVP
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-13-2026 02:46 AM - edited 10-13-2026 02:50 AM
Hi Ellie,
Have you evaluated **Operational Resource Assignments** in Resource Management Workspace for the admin-work allocation?
ServiceNow supports creating operational assignments separately from project/demand assignments. This looks like the closest OOTB fit for your requirement to retain project/demand assignments while allocating a percentage of each person's capacity to admin work.
I'd test this with different admin-allocation percentages for individual resources and verify how those assignments affect the remaining-capacity and utilization views in RMW.
Create resource assignments in Resource Management Workspace
https://www.servicenow.com/docs/r/it-business-management/resource-management/create-ra-rmw.html
If the operational assignments don't provide the required percentage-based flexibility or capacity roll-up in your release, that specific gap needs to be validated before considering customization.
Helpful? Please mark the response as Accepted Solution ✅ and close the thread, this helps future readers find the solution faster.
Regards,
Sachinvic
✨ArchX Certified | ✨ 16x ServiceNow AI MVP
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
@sachinvic - Thank you so much, I actually forgot to accept the solution before, this was offered and accepted. We ended up creating operational resource assignments for the first fiscal year based on assumed allocations, for a more granular use of this feature in future years, appreciate you!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago - last edited 2 weeks ago
No problem at all, @EllieJS ! Glad the suggestion helped.