07-17-2024 07:22 AM
Hi All,
I have a requirement where we need a schedule to run daily, which finds records that will be due in next 5 business days and sends out notification.
Note: The due date can also be in weekends.
Schedule Script:( For this script the notification is triggered for all records in the Problem task table)
var days = 5;
var startDate = new GlideDateTime();
var days1 = parseInt(days); //assuming there are 8 business hours
var dur = new GlideDuration(60 * 60 * 1000 * 24 * days1);
var schedule = new GlideSchedule('sys_id'); //put your schedule sys_id here
var end = schedule.add(startDate, dur);
gs.log('end' + end.getDate());
var notif = new GlideRecord('problem_task');
notif.addQuery('active' , 'true');
//notif.addEncodedQuery('due_dateON'+end.getDate());
notif.query();
while(notif.next()){
if(notif.due_date.getDayOfWeek() < 6){
gs.log('triggered');
gs.eventQueue('problem_task.duedate.notify',notif);
}
}
Any help is appreciated!
Thanks!
Lavanya
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-19-2024 01:49 AM
Hi @Lavanya Nagendr Try below code
var days = 5;
var startDate = new GlideDateTime();
var endDate = new GlideDateTime(startDate);
var businessDaysToAdd = days;
var businessDaysAdded = 0;
while (businessDaysAdded < businessDaysToAdd) {
endDate.addDays(1);
if (endDate.getDayOfWeek() != 1 && endDate.getDayOfWeek() != 7) {
businessDaysAdded++;
}
}
var notif = new GlideRecord('problem_task');
notif.addQuery('active', true);
notif.addQuery('due_date', '>=', startDate);
notif.addQuery('due_date', '<=', endDate);
notif.query();
while (notif.next()) {
if (notif.due_date.getDayOfWeek() != 1 && notif.due_date.getDayOfWeek() != 7) {
gs.eventQueue('problem_task.duedate.notify', notif);
}
}