Need help with level of effort/cost/time to deliver event management within my enterprise
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-27-2016 12:08 AM
Currently looking to stand up Event Management in SN and trying to scope the work. Tying to figure out how to scope things. High level of what we are planing to to
- Configure/set up the event management module
- Integrate with monitoring systems to ensure tight integration with Incident, Problem etc
- Implement best practices
Also would like to know what an ideal time line could be to stand this up and resources needed
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-14-2016 11:12 PM
Tony, Apologies for the late response. This is spot on. I had crafted something while waiting to hear back from the community and it aligns with most of the items you have listed. Thanks a bunch for sending this over. very very helpful.