Hello SNC,
I have a request from the business to create new fields on a catalog item form to capture the start and end date/time of maintenance windows. Furthermore the requestor wants these "maintenance windows" to apply to a calendar so they can view them all on the calendar. (To me this seems similar to what the Change Schedule does so I thought of trying to use that).
What I am trying to do is as follows:
1) I created new fields on the request form (4 sets in total, but for simplicity purposes I'll only mention 2 here.)
the new fields are "Maintenance Window 1 Start Time" and "Maintenance Window 1 End Time" and
"Maintenance Window 2 Start Time" and "Maintenance Window 2 End Time"
2) I have updated the Change Request form with 4 new fields that would match the above fields on the request form.
3) I created a Change Schedule Definition that uses the "Actual Start" and "Actual End" Date/time fields to create the entire window of the ticket.... this seems to work fine
**this is where things seem to get a little wonky**
4) I tried to create a "Related definition" underneath the definition I created as part of Step 3, however I have some roadblocks and questions here....
1st- on the "related records" table, there is a field for "Table Name" and then one for "reference field". Based on what I'm trying to do, I would think table name = change_request would make sense considering the maintenance window fields all exist on the change_request form. The issue is, there's a "reference field" field, and I don't understand what value is supposed to go in there. According to the wiki doc: https://docs.servicenow.com/bundle/london-it-service-management/page/product/change-management/task/add-related-tasks-to-chng-schedule.html
|
This definition is... to say the least... unhelpful.
When I select table name = change_request I have the following options for Reference field
I don't think any of these reference field values makes sense, and I'm not sure how it's determining the list of reference fields to show...
What am I doing wrong here? Essentially I want to be able to create up to 4 different "outage" schedules on the change schedule. This would be based on the fields filled out on the catalog item form. My goal is to add 4 pairs of fields (start/end) for 4-different maintenance windows to the cat item, and then when a ticket gets opened from the portal, a business rule would open a change request, applying the filled-out maintenance window information to the change schedule, and then I can expose the change schedule to the portal so it can be visible to end-users to see the ticket # and related outages on the calendar.
Happy to provide more information if anyone wants to take a stab at this. I don't see much information around the web so it's been challenging just understanding if this is even possible, or if the change schedule with related schedules is meant for something else...
I also have the idea of taking these maintenance window values and having individual change tasks open under the change request, with each change task applying the "maintenance window" to it's "actual start" and "actual end" date fields on the tasks. Would that help? (I might make custom fields instead of using these pre-existing ones)
Thanks in advance,
Dan R
Solved! Go to Solution.
- Labels:
-
Request Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-19-2019 04:59 AM
Hi Dan,
On your Change schedule definition page there should be a related list at the bottom of the page. From there you can create another Change schedule definition related to the primary definition. That will allow you to setup multiple schedules related to the schedule you are using. I'm not sure if it will allow you to do different colors though. I don't recall that being an option on them.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-18-2019 01:43 PM
In essence I have 8 fields on the change request form, and I want all of them to create different color "windows" on the change calendar.
Ex: I have 8 new custom fields on the change_request form: Prep Start/End, Maintenance Start/End, Post Start End/, and Other Start/End. I want all of these fields to show something on the Change Calendar.
Is this possible? If so, how?
Here is an article I found that seems to indicate it is possible:

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-19-2019 04:59 AM
Hi Dan,
On your Change schedule definition page there should be a related list at the bottom of the page. From there you can create another Change schedule definition related to the primary definition. That will allow you to setup multiple schedules related to the schedule you are using. I'm not sure if it will allow you to do different colors though. I don't recall that being an option on them.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-19-2019 06:42 AM