I have resource roles and all roles have their hourly rate set to $0:
However, when I create resource plans, their are still costs that are being calculated:
My assumption is that if all of my hourly rates are set to $0, shouldn't all of my planned costs come to $0 as well? The 'Project Resource' group you see listed above is also set to an hourly rate of $0.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-12-2023 08:17 AM
Check if you have the default hourly rate in Cost properties still set to 50 (this is the ootb default):
(system property com.snc.time_card.default_rate ).
Daniel
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-12-2023 08:17 AM
Check if you have the default hourly rate in Cost properties still set to 50 (this is the ootb default):
(system property com.snc.time_card.default_rate ).
Daniel
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-12-2023 08:20 AM
Thank you! Do you know if this will update historical planned costs from existing resource plans, or does this only affect new plans?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-13-2023 03:30 AM
It won't automatically update. But the Resource Plan should have a "related links" UI Action along the lines of "Update Cost Plan". The PMs can use that to update the cost plans. That should re-apply the hourly rate.