Hello,
I have seen a couple of questions on this but none has any direct answer to the question so I am hoping someone might help. Currently the Actual Start and End Date for Project and Project Task auto-populate the value of the Planned end date whenever the Project is manually closed prior to the Planned end date. I want it to be that we get the current closed date (the date the task was closed) and not the Planned end date in the Actual End Date field.
Product Docs states that when the Derive time component from planned dates is set to True, then this problem occurs but it is currently set to False and we are still experiencing the same issue. Where do I look to resolve this issue?
Thanks for your help.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-17-2019 07:59 AM
Unfortunately this is true. Actual Start and Actual End Dates can be updated after it is saved

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-08-2019 07:26 AM
Hi,
I don't think it's possible to change this behavior, it's an expected behavior after London release, as you said properly documented in the London release note.
There is another discussion about it already there, you can also check here:
If I have answered your question, please mark my response as correct and/or helpful so that others with the same question in the future can find it quickly and that it gets removed from the Unanswered list.
Thank you
Cheers
Alberto
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-17-2019 07:59 AM
Unfortunately this is true. Actual Start and Actual End Dates can be updated after it is saved