02-06-2025 07:27 AM
Hi Community,
I have created a change request on 31-01-2025 14:03:50 (31st Jan) and the planned start date is FEB 6. I have performed Risk assessment on 4th FEB. getting the Risk as high and showing the risk condition as "Insufficient lead time". could some one help me , on what basis this risk condition working. is it considering the risk assessment date. This is the condition defined for "Insufficient lead time. even there is a gap of above 3 business days. it is showing the Risk as high. please find the screenshot and help me out. Thanks in advance @Ankur Bawiskar @Runjay Patel @Sandeep Rajput @Viraj Hudlikar @Rajesh Mushke
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-07-2025 12:00 AM
Hi @raginiv,
Looks like it's an OOB Risk conditions and I don't see any issues with it.
As you are performing the risk on 4th Feb and change planned date is on 6th Feb which means planned start date is less than 3 days so it is automatically setting the Risk as HIGH.
Can you try with the different change with more than 3 days as planned start date, hopefully you will not see the same issue again.
Let me know if you have any other questions.
Thanks,
Rajashekhar Mushke
Rising star : 2022 - 2024
Community Leader -2018
Connect me on LinkedIn : Rajashekhar Mushke
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-10-2025 03:15 AM
Thanks for the information @Rajesh Mushke