Risk condition insufficient lead time trigger based on change created date or Risk assessment date

raginiv
Tera Contributor

Hi Community,

 

I have created a change request on 31-01-2025 14:03:50 (31st Jan) and the planned start date is  FEB 6.  I have performed Risk assessment on 4th FEB. getting the Risk as high and showing the risk condition as "Insufficient lead time". could some one help me , on what basis this risk condition working. is it considering the risk assessment date. This is the condition defined for "Insufficient lead time. even there is a gap of above 3 business days. it is showing the Risk as high. please find the screenshot and help me out. Thanks in advance @Ankur Bawiskar @Runjay Patel @Sandeep Rajput @Viraj Hudlikar @Rajesh Mushke 

raginiv_0-1738855359445.png

 

2 REPLIES 2

Rajesh Mushke
Mega Sage
Mega Sage

Hi @raginiv,

 

Looks like it's an OOB Risk conditions and I don't see any issues with it.

As you are performing the risk on 4th Feb and change planned date is on 6th Feb which means planned start date is less than 3 days so it is automatically setting the Risk as HIGH

Can you try with the different change with more than 3 days as planned start date, hopefully you will not see the same issue again. 

Let me know if you have any other questions. 



Thanks,
Rajashekhar Mushke
Rising star : 2022 - 2024
Community Leader -2018
Connect me on LinkedIn : Rajashekhar Mushke

Thanks for the information @Rajesh Mushke