CMDB Dashboard is calculating both false (Closed complete) and true task to show the heath index percentage. as per the correct behavior it should only calculate the active tasks to calculate the heath index percentage.
5 REPLIES 5
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-12-2025 02:04 PM
@ayush_g Please use CMDB Health inclusion rules to exclude those, there is no such concept of closed complete for a CI as it is just a state of CIs and when computing health results all the CIs are evaluated and these needs to be explicitly excluded if you don't want them.