Update a field in the Resource Plan table from the Resource Workbench
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-23-2024 03:40 AM
Hi,
I created a new field "Percentage" in the Resource Plan table, I was able to show it in the Resource Plan Column in the Resource Workbench and edit it.
When I change the value from the Resource Plan table, I correctly display the updated value in the Resource Workbench but when I change the value directly from Resource Workbench, the value does not save to backend and the "Percentage" field does not update.
How can I update this field directly from Resource Workbench?
Kind regards
Salvatore
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-23-2024 06:17 AM
Hi Salvatore,
Can you check permission for the field. Navigate to the field's dictionary entry (sys_dictionary) and verify that the "Read only" checkbox is unchecked.
Please mark my answer helpful if worked for you.
Thanks