Approvals on Emergency Change

Mego919
Giga Contributor

What is best practice for approvals on an Emergency Change? Is it one approval or two? Should the approval be by a senior leader, CI owner, or change coordinator?

2 REPLIES 2

Harsh_Deep
Giga Sage

Hello @Mego919 

 

Please check below for your answer-

https://ucdavisit.service-now.com/servicehub?id=ucd_kb_article&sysparm_article=KB0001304

 

Mark Correct if this solves your issue and also mark 👍 Helpful if you find my response worthy based on the impact.

Dr Atul G- LNG
Tera Patron

Hi @Mego919 

 

I worked as a change manager and a process lead too. It is tough to say what is a best practice.

But here are few thoughts

- Had minimum 1 approval i.e. ECAB Approval.

- As it is an emergency, I will not recommend to add more approval as it can delay the process.

- If the change is going during the blackout period, and emergency then I prefer to have 1 + 1 means, ECAB + What is best CI owner or Service Owner.

- Also if it compliance changes / then add the other department owner's approval.

 

These are a few tips but it depends on your business nature. 

 

*************************************************************************************************************
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer